How long does production take for 500 jackets, including fabric lead time?
- Share
- Issue Time
- Nov 9,2026
After sample confirmation, 500 jackets take 30–50 days for simple styles with in-stock fabrics, and 60–90 days for complex styles or custom-woven fabric.
Where the time goes: fabric preparation is the first variable — 7–20 days depending on whether the mill holds stock or must weave and dye to order. Cutting, sewing, seam taping and finishing follow, then inspection and packing before ex-factory. Two scheduling tips: (1) lock the sealed sample before bulk starts, because mid-production changes reset the timeline; (2) if your launch date is fixed, ask for a milestone plan with fabric-booking and cut dates visible — an expedited lane exists at most factories, at a defined surcharge rather than a vague promise.