How long does production take for 500 jackets, including fabric lead time?

How long does production take for 500 jackets, including fabric lead time?

After sample confirmation, 500 jackets take 30–50 days for simple styles with in-stock fabrics, and 60–90 days for complex styles or custom-woven fabric.

Where the time goes: fabric preparation is the first variable — 7–20 days depending on whether the mill holds stock or must weave and dye to order. Cutting, sewing, seam taping and finishing follow, then inspection and packing before ex-factory. Two scheduling tips: (1) lock the sealed sample before bulk starts, because mid-production changes reset the timeline; (2) if your launch date is fixed, ask for a milestone plan with fabric-booking and cut dates visible — an expedited lane exists at most factories, at a defined surcharge rather than a vague promise.